Hello Hilton
King George Avenue is NOT being moniored nor repaired at a level to REMOVE the hazards, highlighted by my reports of hazards dated 17, 18, 29, 30 July and 4 August.
There are multiple places where the square edge running parallel to the line of travel exceeds 20mm in depth and are over 2 metres long. This square edge is in the middle of the bike lane and will cause the cyclist to fall into the path of traffic. I have reported this in my latest report (attached) and it is still present at 12 August.
Also, the additional fill is now spread wider across the bike lane.
The attempt to fill some larger holes with cold bitumen has also failed to remove the hazard.
I repeat the above statement... King George Avenue is NOT being moniored nor repaired at a level to REMOVE the hazards.
On 8/14/08, Hilton SOLYOM <HSOLYOM@holdfast.sa.gov.au> wrote:
Dear Sir,
The road is being monitored and repaired by depot staff, until it will be resealed
Yours faithfully,
Hilton Solyom
Technical Engineer City of Holdfast Bay
É 08 8229 9939
Ê 08 8298 4561
www.holdfast.sa.gov.au